This Week’s RERA Orders, Explained for Agents

The RERA orders and directions that change how you should advise buyers. Each one in plain English: what happened, what it means for you, what to say to buyers, and a 2-question check.

This Week at a Glance
  1. Uttar Pradesh: UP-RERA bans blanket consent for building plan changes
  2. Maharashtra: Later project extension can’t cancel a buyer’s refund right
  3. Haryana (Gurugram): Gurgaon buyer who exited a delayed Ireo project loses ₹1 crore compensation claim
  4. Punjab (Tricity): Buyers who stay in a delayed project get delay interest, not compensation
How we label cases: Reported facts are from a published order report or two or more outlets. Headline only only the headline has been seen and the full order has not been reviewed yet, so we stick to what was reported and the settled law around it. Sources are linked under every case.
Case 2 7 Nov 2026 · Maharashtra Reported

Later project extension can’t cancel a buyer’s refund right

A Pune buyer in Godrej Forest Grove asked to withdraw and get a refund after the agreed possession date (30 Sep 2024) passed. The builder later got the project’s RERA registration extended to 2027 and argued the possession date moved too. MahaRERA disagreed and ordered a full refund with interest.

Key Facts
  • Agreement for sale signed November 2020; possession promised by 30 September 2024; buyer had paid about ₹25 lakh.
  • Buyer sought withdrawal and refund on 28 May 2025. The builder obtained a registration extension on 20 August 2025, moving project completion to 30 September 2027.
  • MahaRERA held that a later extension cannot take away a withdrawal right already used, and that extending registration does not change the possession date in the agreement.
  • Because this was a statutory withdrawal under Section 18(1)(a), not a voluntary cancellation, the builder’s 2% and brokerage deductions were refused.
  • Relief: refund (excluding stamp duty, registration, GST and other taxes) with interest at SBI’s highest MCLR + 2% from each payment date. Separate claims for mental agony were refused, because Section 18 interest is itself compensatory.
Forum: MahaRERA (Member Ravindra Deshpande) · Law: RERA Act 2016, Section 18(1)(a)
What it means for agents
The possession date that counts is the one in the agreement for sale, not the date on the RERA portal after an extension.
When a project is late, buyers have a real choice between withdrawing and staying. Explain both honestly; don’t steer them for your own commission.
Builder deductions that apply to a buyer’s voluntary cancellation don’t apply when the buyer exits because the builder was late.
💬 Say this to buyers
“Your possession date is the one in your agreement. If the builder misses it, you can ask to exit with a refund and interest, and a later RERA extension doesn’t take that away.”
✅ 2-Question Check
1. A builder misses the agreement’s possession date. The buyer asks to withdraw. Three months later the builder gets the RERA registration extended. Per this MahaRERA order, what happens?
2. Why were the builder’s 2% cancellation and brokerage deductions refused?
Sources: LiveLaw Business, 7 Nov 2026 (Kapil Ashokrao Gahukar v Godrej Skyline Developers Ltd)
In the RCP course: IC03 Lesson 6 (Section 18)
Case 3 Nov 2026 · Haryana (Gurugram) Headline only

Gurgaon buyer who exited a delayed Ireo project loses ₹1 crore compensation claim

ETRealty reports that a buyer who left a delayed Ireo project in Gurgaon lost a compensation claim of about ₹1 crore. As reported, the promoter argued that the agreement was signed before the RERA Act and that the buyer had defaulted on payments despite reminders. We have not yet reviewed the full order, so we are not stating the reasons the forum gave.

Key Facts
  • Reported claim: about ₹1 crore compensation against Ireo, for a delayed project in Gurgaon.
  • Promoter’s reported arguments: the agreement pre-dated the RERA Act, and the buyer defaulted despite payment reminders.
  • Forum, date and the exact reasoning: not yet verified by RERACertified.
Forum: Not confirmed (as reported by ETRealty) · Law: RERA Act 2016, Sections 18 and 19(6)–(7)
What it means for agents
Whatever the reasons in this order, RERA rights work both ways. Under Section 19(6) and (7), buyers must pay on time and pay interest when they are late.
A buyer who stops paying to “pressure the builder” can weaken their own claim. Never give that advice.
Older, pre-RERA agreements are a common battleground in delayed projects. Ask for the agreement date and payment record before discussing any claim.
💬 Say this to buyers
“Keep paying as per your schedule and keep every reminder and receipt. If you fall behind, it can hurt your claim later, even if the builder is late.”
✅ 2-Question Check
1. Which section of the RERA Act puts a duty on the buyer to make payments on time as per the agreement?
2. A buyer asks if they should stop paying instalments to put pressure on a late builder. Best advice?
Sources: ETRealty (headline only; full order not yet reviewed)
In the RCP course: IC03 Lesson 6 (Section 19 obligations)
Case 4 24 Sep 2026 · Punjab (Tricity) Reported

Buyers who stay in a delayed project get delay interest, not compensation

Buyers of a 3BHK in Sushma Buildtech’s project at Gazipur, Derabassi (Mohali district) sought ₹5 lakh for mental agony plus other losses for late possession. They had chosen to continue in the project and had already been given delay interest. Punjab RERA’s Adjudicating Officer dismissed the compensation claim.

Key Facts
  • Agreement dated 17 November 2020; possession due 19 May 2022.
  • The buyers had sold a Panchkula property to buy the flat and claimed mental agony, lost capital-gains benefit, rent and interest costs.
  • Held: under Section 18(1), compensation is for an allottee who withdraws. One who continues gets interest for every month of delay until possession.
  • An earlier RERA order (25 Feb 2025) had already granted delay interest, so the further claim was dismissed.
  • Case: Renu Choudhary & Anr v M/s Sushma Buildtech Ltd (AdC No. 0083 of 2022).
Forum: Punjab RERA Adjudicating Officer R.S. Rai · Law: RERA Act 2016, Sections 18(1) and 71; Punjab RERA Rules, Rule 37
What it means for agents
Stay or exit is a big decision with different outcomes: continuing means delay interest; withdrawing means refund with interest and a possible compensation claim.
Don’t promise Tricity buyers “compensation” for delay if they plan to stay in the project.
Refund and interest go to the RERA Authority; compensation claims go to the Adjudicating Officer.
💬 Say this to buyers
“If you stay in the project, RERA gives you interest for every month of delay. Compensation on top is generally for buyers who exit. Let’s look at which suits you.”
✅ 2-Question Check
1. Per this Punjab RERA order, what is a buyer who chooses to continue in a delayed project entitled to?
2. Who decides compensation claims under the RERA framework?
Sources: LiveLaw Business, 1 Oct 2026
In the RCP course: IC03 Lesson 6 (Section 18)
Agent Script: Builder Consent Letters

Word-for-word lines (English and Hinglish) for when a builder asks you to collect consent signatures, or a buyer asks “should I sign this?”

Read the script →

Frequently Asked Questions

What is RERA Watch?
A weekly page from RERACertified that picks the RERA orders and regulator directions that matter most to real estate agents, explains each in plain English, and says what an agent should do and tell buyers.
How often is RERA Watch updated?
Every week. New cases go at the top, and older cases stay on the page as a running archive.
Are these the official orders?
No. RERA Watch summarises orders and directions as reported by named sources, which are linked under each case. Each case is labelled “Reported” (from an order report or two or more outlets) or “Headline only” (full order not yet reviewed). Always read the official order before relying on it.
Is this legal advice?
No. It is general information for learning. For a specific dispute, the buyer should read the order and take advice from a lawyer.
Are these cases in the RERACertified course?
Yes. Key cases are added as case files inside the matching RCP lesson, mostly IC03 (RERA Act 2016), so students see the rule and a live example together.
Change Log
Nov 14, 2026: RERA Watch launched with 4 cases (UP-RERA blanket consent, MahaRERA withdrawal vs extension, Ireo Gurgaon claim, Punjab RERA delay interest).
Learn the Rules Behind Every Case

RERACertified™ Professional covers the RERA Act section by section, your state’s rules, and real case files like these, ending in a QR-verifiable certificate.

See the course →

RERACertified is a private training provider, not a RERA authority. This page is general information, not legal advice.